1) That
Members resolve to: Delegate Authority to the Chief Planning
Officer to GRANT planning permission, including the imposition of
relevant conditions and informatives as summarised below and those
as may be deemed necessary by the Chief Planning
Officer:
Conditions:
·
Standard 3-year time limit
·
Approved plans
·
Sustainability measures (broadly in accordance
with the proposed measures submitted under the application-
including EV charging points and PV panels) to be
submitted
·
Construction Environmental Management Plan to be
submitted
·
Biodiversity Enhancement Strategy to be
submitted
·
Wildlife Sensitive Lighting Scheme to be
submitted
·
Fire hydrants to be submitted
·
Archaeological Written Scheme of Investigation to
be submitted
·
Archaeological Post Investigation to be
submitted
·
Surface Water Drainage and Flood Risk Assessment
Strategy implemented
·
Surface Water Drainage Verification Report to be
submitted
·
Construction Surface Water Management Plan to be
submitted
·
Visibility splays to be provided in full and no
obstruction to be within those splays.
·
Parking provision provided in full
·
Details of means to prevent surface water
entering highway to be submitted
·
Bin storage and presentation areas to be
submitted
·
Construction Management Plan to be
submitted
·
Access upgrades to be implemented
·
Temporary cabins to removed from site 1 year after
commencement
·
Travel Plan to be submitted
·
Notwithstanding the provisions of F1 use class,
the building shall be exclusively for delivery of construction and
agricultural training
·
Container storage shall solely be used for
incidental purposes to the construction and agricultural
training
·
Arboricultural report to be adhered
to
·
Materials details of all buildings (including
colours) to be submitted
·
Soft landscaping plan to be
implemented
·
Notwithstanding soft landscaping further
landscaping details of SuDS to be
submitted
·
Notwithstanding soft landscaping plan, additional
information on root barrier membranes to be submitted
·
Landscape Management Plan to be
implemented
·
Hard Landscaping details to be
submitted
·
Equestrian land used for private use- no
commercial equestrian use permitted
·
Site Management Plan to be submitted
·
Independent noise assessment to be carried out
prior to first use
·
Construction and agricultural activities shall be
confined to the dedicated areas on site plan
With the
additional conditions as included in the Tabled Papers:
·
Notwithstanding the submitted information,
details of boundary treatment (soft and hard) along the Public
Right of Way and between the equestrian and training area to be
agreed
·
If the telehandler training tower is no longer in
active use it will be removed from the site.
Informatives:
·
Positive working with NPPF pre-app
·
National Highways recommended notes
·
SCC Highways recommended notes
·
SCC Public Rights of Way recommended
notes
·
SCC Floods and Water recommended
notes
·
Environment Agency recommended notes
·
East Suffolk Drainage Board recommended
notes
And the
additional conditions from the committee:
·
Restriction on height of container
stacking
·
Horse manure storage and removal
·
Fuel storage details
·
Hours of operation and use of
machinery
·
Advance landscaping installed
·
Provision of PV panels
·
Details to be agreed for equipment use numbers
and machinery, based on noise assessment, including interaction
with PROW
·
No tonal reversing sensor to be
used