Resolution status:Carried
It was RESOLVED: -
1.1 That the CIL Expenditure Programme (March 2022) and accompanying technical assessment of the CIL Bid – M22-13, M22-02, and M22-14 (forming Appendices, A and B) and which include decisions on these CIL Bid for Cabinet to make and approve and to note (delegated decision only) are as follows: -
Decisions for Cabinet to make: Local Infrastructure Fund
CIL Bid, Location and Infrastructure Proposed |
Amount of CIL Bid and total cost of the Infrastructure |
Cabinet Decision |
M22-13 RINGSHALL Play Area
|
Amount of CIL Bid £20,566.35 Total costs of the project £54,856.08 Other funding sources are Ringshall Parish Council Neighbourhood CIL Reserves £16,000.00 Donation £1,000.00 Fundraising £350.00 MSDC Community Grant £16,939.73 |
Recommendation to Cabinet to approve CIL Bid M22-13 for £20,566.35 from the Local Infrastructure Fund |
Decisions for Cabinet to make: Strategic Infrastructure Fund
CIL Bid, Location and Infrastructure Proposed |
Amount of CIL Bid and total cost of the Infrastructure |
Cabinet Decision |
M22-14 THURSTON Rail Feasibility Study
|
Amount of CIL Bid £100,000.00 Total costs of the project £100,000.00
|
Recommendation to Cabinet to approve CIL Bid M22-14 for £100,000.00 from the Strategic Infrastructure Fund (with the awarded unspent funds (£100,000) under the previously approved CIL Bid M20-07 for Thurston Rail station feasibility study being returned to the Ringfenced Infrastructure Fund (Thurston) after the 11th September 2022 when the 2 year CIL Bid offer letter expires). |
Decisions for Cabinet to note: Ringfenced Infrastructure Fund (Botesdale)
CIL Bid, Location and Infrastructure Proposed |
Amount of CIL Bid and total cost of the Infrastructure |
Cabinet Decision |
M22-02 BOTESDALE Recreation Ground Entrance Infrastructure and picnic tables
|
Amount of CIL Bid £9,757.50 Total costs of the project £13,010.00 Other funding sources are Botesdale Parish Council £3,252.50 |
Recommendation for Cabinet to note the delegated decision for CIL Bid M22-02 for £9,757.50 from the Ringfenced Infrastructure Fund (Botesdale) |
1.2 Cabinet was also asked to note and endorse this CIL Expenditure Programme which includes the position in respect of approved CIL Bids from Rounds 1, 2, 3, 4, 5, 6, 7, 8 and 9 - (Appendix A Section B) together with details of emerging infrastructure /CIL Bids (Appendix A Section C.
1.3 That with reference to the Thurston Infrastructure project (M22-14) the Portfolio Holder for Planning, the Director for Planning and Building Control and the Ward Members for Thurston collaborated on the covering letter.
Vote | Councillors | Count |
---|---|---|
For | Gerard Brewster, David Burn, Jessica Fleming, Peter Gould, Lavinia Hadingham, Suzie Morley, Harry Richardson and John Whitehead | 8 |
Against | None | 0 |
Abstain | None | 0 |
Conflict Of Interests | None | 0 |