Resolution status:Carried
It was RESOLVED: -
1.1 That the CIL Expenditure Programme (November 2022) and accompanying technical assessment of the CIL Bids – M21-09, M22-06, M22-12, M22-15, M22-05 and M22-09 (forming Appendices, A and B) and which include decisions on these CIL Bid for Cabinet to make be approved and noted (delegated decision only) as follows: --
Decisions for Cabinet to make: Ringfenced Infrastructure Fund (Walsham-le-Willows, Badwell Ash, Thurston, Elmswell, Woolpit, Tostock and Rattlesden) and Strategic Infrastructure Fund
CIL Bid, Location and Infrastructure Proposed |
Amount of CIL Bid and total cost of the Infrastructure |
Cabinet Decision |
M21-09 THURSTON Expansion of Thurston Community College
|
Amount of CIL Bid £1,781,462.00 Total costs of the project £2,018,011 Other funding sources are Section 106 £184,595 Basic Need funding £33,943 Suffolk County Council borrowing £18,011 |
Recommendation to Cabinet to approve CIL Bid M21-09 for £1,214,468.96 from the Ringfenced Fund (Walsham-le-Willows, Badwell Ash, Thurston, Elmswell, Woolpit, Tostock and Rattlesden) and £566,993.04 from Strategic Infrastructure Fund |
Decisions for Cabinet to make: Local Infrastructure Fund
CIL Bid, Location and Infrastructure Proposed |
Amount of CIL Bid and total cost of the Infrastructure |
Cabinet Decision |
M22-06 EYE Play Facilities
|
Amount of CIL Bid £100,000.00 Total costs of the project £150,000.00 Other funding sources are MSDC Capital Grant £25,000.00 Eye Town Council £5,000.00 Community Development Fund MSDC £20,000.00 (unsecured) |
Recommendation to Cabinet to approve CIL Bid M22-06 for £100,000.00 from the Local Infrastructure Fund (CIL Funding is subject to other funding being secured) |
M22-12 OLD NEWTON Village Hall Extension
|
Amount of CIL Bid £67,914.00 Total costs of the project £90,552.00 Other funding sources are S106 funding £861.57 Capital Grants MSDC £21,776.43 |
Recommendation to Cabinet to approve CIL Bid M22-12 for £67,914.00 from the Local Infrastructure Fund |
M22-15 WETHERDEN Play Area |
Amount of CIL Bid £18,375.63 Total costs of the project £33,375.63 Other funding sources are Wetherden Parish Council £15,000.00 |
Recommendation to Cabinet to approve CIL Bid M22-15 for £18,375.63 from the Local Infrastructure Fund |
Decisions for Cabinet to note: Local Infrastructure Fund
CIL Bid, Location and Infrastructure Proposed |
Amount of CIL Bid and total cost of the Infrastructure |
Cabinet Decision |
M22-05 EYE Moors Woodland Footpath
|
Amount of CIL Bid £5,000.00 Total costs of the project £13,000.00 Other funding sources are Suffolk County Council and Eye Town Council £2,000.00 CLA Charitable Trust £6,000.00 |
Recommendation for Cabinet to note the delegated decision for CIL Bid M22-05 for £5,000.00 from the Local Infrastructure Fund |
M22-09 METFIELD Play Area |
Amount of CIL Bid £8,788.97 Total costs of the project £11,718.63 Other funding sources are MSDC Locality fund £2,000 Metfield Parish Council £125.67 S106 funding £803.99 |
Recommendation for Cabinet to note the delegated decision for CIL Bid M22-09 for £8,788.97 from the Local Infrastructure Fund |
Cabinet also noted and endorsed this CIL Expenditure Programme which includes the position in respect of approved CIL Bids from Rounds 1, 2, 3, 4, 5, 6, 7, 8 and 9 (September 2022) - (Appendix A Section B) together with details of emerging infrastructure /CIL Bids (Appendix A Section C).
Vote | Councillors | Count |
---|---|---|
For | David Burn, Julie Flatman, Jessica Fleming, Lavinia Hadingham, Suzie Morley, Harry Richardson and John Whitehead | 7 |
Against | None | 0 |
Abstain | None | 0 |
Conflict Of Interests | None | 0 |